The Knolls

Progress

The general contractor.
December 2, 2004
The staff of the general contractor taking ownership of the project.
The interior showing the bracing uses to stabilize the forms
December 2, 2004
The empty forms are stabilized with bracing in preparation for pouring the walls, that is, filling the forms with concrete.
The view through the window of the bedroom.
December 2, 2004
This is the view through the master bedroom window. It will be better without all the bracing!
Concrete pumper.
December 3, 2004
The concrete is pumped from the supply truck to the required location at the top of the forms. The forms stay on the wall after it has cured, providing interior and exterior insulation.
Pouring the lakeside wall.
December 3, 2004
More pouring.
Pouring the wall on the lakeside.
December 3, 2004
More pouring. This step makes the project even more real!
Framing the interior.
December
After clearing out the bracing, the framing of the interior walls takes place.
Framing the interior.
December
Diane walking along the main corridor, real and perceived.
Framing the interior.
December
The view from the study space, through the second bathroom to the main living space.
Framing the interior.
December
View from the study to the great room.
Installing the roof trusses.
January 5
The roof trusses arrived before Christmas but weather and holidays kept their installation from starting until the new year. You see the plywood for the roof ahead of you.
It was a cold day on the 5th, but the previous day was spring-like. Even on the cold day the framers were working with bare hands. Just holding the camera to take these pictures made my digits ache for a half hour!!
View from the beach.
January 5
With the roofline defined, the structure starts to take on a real presence from the shoreline, as this and the next couple of images show.
View from the beach (east).
January 5
The windows are big.
View from the beach.
January 5
And the access through the garden doors is generous.
Interior framing with trusses in place.
January 5
More framing ... it is possible to get a sense of the individual spaces now, although the kitchen is not yet framed up.
Interior framing with trusses in place.
January 5
Photographer inspired?
View from the road.
January 11
This is a view from the road just before entering the property. A black roof will not be too obvious from the street.
The garage.
January 11
The garage with the roof deck in process.
The team on the roof.
January 11
The temperature was about -8  C.
From the well head.
January 11
Today the pump had been installed, readying the well for pumping when the hydro is hooked up.
View from the lower path.
January 11
The shapes and the volumes become more evident now. The gable is being built using the on-site stick method, unlike the rest of the roof support which was pre-built trusses.
First ice on the beach.
January 11
This is the first ice on the shore this year. It is hard to believe that the lake might freeze over this year.
The gable from inside.
January 11
In the same way that the volumes and shapes are defined in the outside views, the interior spaces are also taking shape.
Looking through the mudroom to the garage.
January 11
Each day there is a new definition of the space, leading to anticipation of how it will be used.
Strapping for the siding.
January 16
The garage is wrapped, and strapped as is the north side of the structure. The ice protector is starting to be installed on the roof. The bundles of shingles are on the roof waiting for the roofer. It has been very cold, with wind chill down to minus 25, so it is not surprising that the progress has slowed.
The lake iceing over for the first time.
January 16
Today was the first time the lake had iced over. Very thinly, but iced over. The water birds were quite distressed at this occurence.
The roofers' achievement.
January 25
Much to my surprise when I visited the site today, after a week's intense cold and two snowstorms, the roofers had installed the shingles. They are known in the industry as "hurricane" shingles, by brand, Weathertite" and are not usually found in this part of the country. We found about them only by chance and there is a limited supply since they were introduced to only to maintain a supply in building materials yards when another variety was in short supply. This is the better shingle. Shadow Black is the name.
Framing the kitchen.
January 25
The kitchen is a complicated space for framing with its pass-throughs, half-height walls, etc. and additionally complicated by the presence of a notional kitchen drawing that the builders were looking at and modifying the original drawing projection somewhat. However, a review this morning got things straight.  Looking west to the living room.
Framing the kitchen.
January 25
Richard Harper of Kitchen Kraft arrived while I was there this morning. He is the neighbour to the north, and is looking after the kitchen design, etc. Looking east to the bedroom.
The gable windows in place.
January 25
The first windows installed are in the gable. The black Obsidian looks very handsome. The windows are by Weathershield, supplied by The Window Center in Kingston. Not quite the Mercedes of windows, but very close.
Installing one of the operating windows in the master bedroom
January 26
The windows were delivered this morning at 10 a.m. By 2 p.m. they were almost all installed.
Interior with windows installed
January 26
The installation of the windows makes a major difference to the interior especially when the  outside temperature is 12 C below, and the wind is adding another 10 degrees of wind chill!
Windows installed from the shoreline.
January 26
Glazing in the windows adds reflection to the effect of the facade.
The whole view.
January 26
The whole view of the facade with windows installed.
Exterior view from the dining room.
January 26
This is the view from the interior of the dining room.
On the beach in winter!
January 27
The fall of boulders on the beach is covered with ice and snow, save a few. This has been a very open winter until now.
Shore to west from the beach.
January 27
Looking to the west mid-afternoon.
Looking to the east from the beach.
January 27
Looking to the east mid-afternoon.
View of the house from the beach.
January 27
With all the windows in, it really does look like a house from the beach.
Wendy and David "on ice".
February 3
Finally Wendy and David, my close friends, come to the site.
The ice.
February 3
Off the shore the ice buckles up and pushes over the ice in the shallows.
More ice.
February 3
More ice. The temperature was about 4 degrees C. today. Is this a bishop or a rabbit?  The ice was thrown up in a variety of shapes and sizes. What do you think?
>>>>>>>>>>>

 Go to the Next Page
<<<<<<<<<<<
 Go to Previous Page

Home
Location The History

The Plans The Progress
Links
Webmaster: one AT bellonart.net (replace the AT with @)  <<<<<>>>>>  Last Updated February 3, 2005