The Knolls

Progress

  • Clicking on the small image to the left will bring up a larger version.
  • To return to this page use the "Back" button on  your browser.
  • To return to the PREVIOUS PAGE.
March 24
Getting the drywall up.
The "boarding" has finally started. The last month was consumed with getting all the behind the walls things completed -- sound system, alarm system, and just generally getting all the details of cabinetry and other finishes decided. The drywall folks were late in starting, being in high demand.
March 24
The fireplace end of the living room.
The "board" is large dimension, 54 inches by 12 feet. It covers a lot, but it is heavy to move around. The west end of the living room is looking good. One never knows until this stage is reached.
March 24
Boarding the cathedral gable.
The gable from the interior fulfills the function of a "chimney" to vent any excess heat in the summer and draw cool air in from the cool side of the house, either the north or the east. Passive solar requires the occupant to "run" the house to keep it comfortable without using a lot of expensive air conditioning.
Garage interior.
April 6
The garage doors are installed, although the installers mismatched the colour by a small degree. They will be back!
Parging.
April 6
The break in the weather makes it possible to do the parging to protect the exposed insulation at the grade level.
Siding started.
April 6
The siding, Eastern cedar, is now on site after a considerable delay. It is being supplied by Loyalist Forest Products, near Tamworth. The siding will be stained a dark olive colour.
Taping and mudding.
April 6
The final stages of boarding and the start of the taping and mudding.
Taping and mudding.
April 6
The boarding and taping is being completed by the Paul Brothers.  View from the study door along the interior "corridor".
Derek and Richard.
April 6
Derek Dowling, the project supervisor for Wemp and Smith, and Richard Harper of Kitchen Kraft (Kingston) confirming the kitchen counter measurements, viewed through the dining room from the bedroom door.
Boarding and taping completed.
April 6
The sanding is completed. Now for the clean-up to prepare for the painters.
The siders are to the front.
April 11
The siders have progressed to the front, working in the gable area.
The painter.
April 11
Self-explanatory.
The interior first coat - hazy skies.
April 13
This is the final colour for the ceiling and the walls -- hazy skies, Benjamin Moore's Collection Series.
Clearing the floor.
April 14
The protection of the floor has been removed in anticipation of the staining stage.
Set in Concrete
April 15
The floor staining contractor is Set in Concrete from Coburg, Ontario.
Bob Engelbert6
April 15
Bob Engelbert is "Set in Concrete".
Staining the floor.
April 15
View along the window corridor from outside, through the east window. The floor is masked in areas where the stain will be lighter in colour. This green colour will transform into Malay Tan by Kemiko.

Problem: the stain did not take. Another strategy will be followed to get a surface that will stain. The problem seems to be that the trowelling was too "thorough" and the sureface became too "tight" to absorb the acid properly. Wait for the next instalment. In the meantime the other trades will finish their work and Bob will come back in when the materials and his schedule permit in early  May. Much disappointment all around.
Siding completed.6
April 15
The siding is completed, leaving the trim and the shade device to be installed next week. We are very pleased with the way the siding has turned out. Of course, that is because it is the most visible aspect of the house, but we are very, very pleased with all the other aspects of the house too!
Trimming the windows.
April 21
The siding trim has an elegant half inch moulding. This corner is an indication of the high quality of the work done by the siders.
Constructing the shade device.
April 21
The shade device is very pragmatic in its design and fabrication -- done on the spot. It can serve as a trellis for vines if necessary to keep the summer sun from heating up the house too much.
The siding team.6
April 21
The siding team at work.
Installing the cables.
April 21
Under the gable, the shading device is supported by cables.
The shadow.
April 21
The shade device will throw a dynamic shadow on the facade and on the interior as the sun moves through the day.
The bog.
April 21
The other "water feature" -- a springtime bog to the east of the house. It is a favourite place for the herons to feed.
>>>>>>>>>>>
 Go to Next Page
>>>>>>>>>>>
 Go to Previous Page

Home
Location The History The Plans The Progress Links
Webmaster: one AT bellonart.net (replace the AT with @)  <<<<<>>>>>  Last Updated April 21, 2005